Construction Update

eNotify
Sign up to receive e-mail notification
when Construction Updates are posted!

Capital Improvement Projects
Updated 10/17/2008 3:34:42 PM

Construction Update


CANYON COUNTRY

SIERRA HIGHWAY BRIDGE(S) OVER THE RAILROAD - NO. S3009
Sierra Highway Bridge over the Metrolink Railroad between Canyon Park Boulevard and Flying Tiger Drive
This project will provide the environmental clearance, design, right-of-way acquisition, and construction for the replacement of the northbound bridge and the rehabilitation of the southbound bridge on Sierra Highway crossing over the railroad to accommodate six lanes of traffic. Project Information Line (661) 290-2295.
Current Status: Construction complete pending City Council acceptance
Traffic Impacts: Minimal impacts anticipated
Project Contact Information
Permitee: Griffith Company
Other Contact Information: cip@santa-clarita.com
Project Manager(s): Terry Brice

VIA PRINCESSA METROLINK RESTROOMS AND SEWERS DESIGN
Weyerhaeuser Way at Via Princessa
Project No. F3012 will add restrooms and public sewers to the existing Via Princessa Metrolink Station.
Current Status: Construction is ongoing.
Estimated Completion: 10/13/08
Traffic Impacts: Moderate
Project Contact Information
Permitee: City of Santa Clarita
Inspector: Fred Bonilla
Project Manager(s): Tara Concepcion


CITY-WIDE

2007-2008 OVERLAY & SLURRY PROJECT
Various Streets though-out City
Asphalt overlay and slurry seal of various streets. Maps of designated areas can be found at http://www.santa-clarita.com/cityhall/pw/cip/

Current Status: Construction is ongoing.
Estimated Completion: 10/02/08
Traffic Impacts: Daily lane closure with flag men
Project Contact Information
Permitee: Silvia Construction
Inspector: Fred Bonilla
Project Manager(s): Frank Lujan

INCIDENT MANAGEMENT - TRAVELER INFORMATION SUBSYSTEM I0004
Citywide
The City received a $950,000 grant from the Metropolitan Transportation Authority (Metro) to install traveler information data collection, and to further integrate and disseminate the information within the City.
Current Status: Construction is ongoing.
Estimated Completion: 1/31/09
Traffic Impacts: Minimal impacts anticipated
Project Contact Information
Permitee: TDS Engineering
Inspector: David Ramos
Project Manager(s): Terry Brice


PARKS RELATED

SANTA CLARITA SPORTS COMPLEX PHASE IV GRADING & DRAINAGE DESIGN
Centre Pointe Parkway and Reuther Avenue
Grading & drainage design for Phase IV of the Sports Complex, Project No. P3012.
Current Status: Construction is ongoing.
Estimated Completion: 02/01/09
Traffic Impacts: Minimal impacts anticipated
Project Contact Information
Permitee: Sukut Construction
Inspector: Evan Aldrich
Other Contact Information: Balvinder Sandhu
Project Manager(s): Tara Concepcion, Balvinder Sandhu


VALENCIA

CASTAIC LAKE WATER AGENCY WATER LINE INSTALLATION
South Fork bike trails
CLWA will be installing water line on Valencia Boulevard from Bouquet Canyon Road to Magic Mountain Parkway, on Magic Mountain to Railroad Avenue, and then down to Drayton Street. The second phase of the water line will be on the south fork bike trails between McBean Parkway and Valencia Boulevard.
Current Status: Construction is ongoing.
Estimated Completion: 12/15/08
Traffic Impacts: Night time road closure
Project Contact Information
Permitee: Castaic Lake Water Agency
Inspector: Mark Lindemann
Project Manager(s): Mark Lindemann

MAGIC MOUNTAIN/I-5 PHASE II - DESIGN AND OVERSIGHT - PROJECT NO. S1002
Magic Mountain Parkway; The Old Road; I-5 on and off ramps at Magic Mountain Parkway Interchange
The City of Santa Clarita is overseeing the construction of phase 2 improvements, a joint City-Developer effort to reconstruct the I-5 Magic Mountain Interchange. This includes various construction activities in Los Angeles County & Caltrans' jurisdictions. There are a total of 11 phases for these improvements. The anticipated completion date is by Fall of 2009. Project Information Line (661) 290-2297.
Current Status: Construction is ongoing.
Estimated Completion: 11/30/2009
Traffic Impacts: Night-time ramp closures and traffic detours may affect drive time.
Project Contact Information
Permitee: Security Paving
Inspector: Fred Bonilla
Project Manager(s): Harry Corder, James Tong

SANTA CLARA RIVER COMMUTER TRAIL SEGMENT 1 - PROJECT NO. T0017
North of Magic Mountain Parkway/Tourney Road to Anza Drive
This project will provide for the design and construction of Segment 1 of the Santa Clara River Trail. This segment will extend from the terminus of Anza Drive to Interstate 5. Original project scope was for three segments, which includes Segments IV and V, that extend from Bouquet Canyon Road to the City-owned river park site in Canyon Country.
Current Status: Construction is ongoing.
Estimated Completion: 12/01/2008
Traffic Impacts: none
Project Contact Information
Inspector: Dave Ramos
Project Manager(s): Amalia Marreh


 


Parks Construction

CITY OF SANTA CLARITA - CANYON COUNTRY PLAYGROUND UPGRADES
17615 West Soledad Canyon Road

Project includes removal of existing play structure and installation of concrete sub-grade, new play structure, and resilient surfacing.

Current Status: Construction to commence 08/18/08
Completed: 10/14/08
Traffic Impacts: Minimal impacts anticipated
Project Contact Information
Permitee: Fleming Environmental
Inspector: To be assigned
Project Manager(s): Denise Clark

CITY OF SANTA CLARITA - LOST CANYON TRAILHEAD

Intersection of Lost Canyon Road and Woodfall Road to approximately 500 feet southwest along Woodfall Road, directly south of SR, 14, Santa Clarita.

Project includes minor grading and installation of gravel and decomposed granite, planting, irrigation, drinking fountain, benches, and hitching post.

Current Status: Construction to commence 10/21
Estimated Completion: 12/08
Traffic Impacts: Minimal impacts anticipated
Project Contact Information
Permitee: John Burgeson Construction
Inspector: To be assigned
Project Manager(s): Denise Clark
 
CITY OF SANTA CLARITA - SANTA CLARITA SPORTS COMPLEX PHASE IV

Phase IV improvements will be made on 14 acres at the Sports Complex. Amenities to include: a new expanded skate park, a turf practice field, a temporary dog park, two basketball courts, additional parking lots, restroom/maintenance building and landscape improvements. Current Status: Construction to commence 08/08

Estimated Completion: Summer 2009
Traffic Impacts: Minimal impacts anticipated
Project Contact Information
Permitee: Valley Crest Landscape Development (Pending Award)
Inspector: To be assigned
Project Manager(s): Glenn Bogna

Construction Links: